Multi-lateral Development Bank Funded Project (IMF) – Cite Soleil, Haiti

Reference Project:  E-Power, Cite Soleil Plant Commissioning, Permitting, Environmental Mgmt

Brief Description:  ESS responsible for initial certification and commissioning support, permit modifications and all relevant air, soil, water and noise sampling for initial and ongoing compliance with IFC requirements.  ESS project participation continuously since 2012.

US Government Managed Project/US EPA (AirNow) Agency Oversight

Reference Project(s):  US State Department (and UNIS) installed and managed ambient air stations

Brief Description:  ESS was contracted for the initial installation of three (3) ambient air stations within Viet Nam (US Embassy and UNIS in Ha Noi and US Consulate in HCMC) as part of the US EPA Managed Air Now Network.  ESS provides all IT, interfacing and maintenance/repair services as required by contract.

Daewoo Engineering and Construction – Morroco

Reference Project:  Pre-Commissioning Activities, Commissioning Activities, CEMS/COMS and PM CEMS Certification and verification

Brief Description:  ESS responsible for development of point source measurement protocol; conduct of sampling and analysis; issuance of confirmatory and summary reports; soil sampling and analysis for corroboration to emission data; sourcing and installing temporary CEMS for continuous monitoring of stack emissions.

Chip Mong Insee Cement Corporation – Cambodia

Reference Project:  Emissions Testing

Brief Description:  ESS conduct emissions testing on the main stack; emissions sampling on three (3) other non-combustion stacks; and, CEMS/COMS audit and annual service for the Facility referenced as Insee Cambodia Chip Mong Cement Plant – Cambodia

RITCO – Royal Industrial Technical Corporation – Indonesia

Reference Project: CEMS Certification – Gaseous Criteria Pollutants, Flowrate, Dust/PM & Opacity
Brief Description:  ESS conduct 40 CFR Part 60/75 Continuous Emission Monitoring System (CEMS) Relative Accuracy Test Audit and certification services.  The plant has a World Bank funding component.

Daelim San Buenaventura Philippines – Philippines

Reference Project:  Unit 1 Performance Testing (isokinetic and gaseous), Water Testing, Ash/Coal Sampling for overall equipment performance, CEMS/COMS and PM CEMS Certification
Brief Description:  ESS is responsible for assessing (including sampling and analysis) the indoor air quality in UNHCR offices, consulting and providing mitigation services for client locations.

US Government/CH2M Hill Managed – Johnstoll, United States

Reference Project:  USAFCEE Herbicide Orange Remediation Project

Brief Description:  ESS responsible for development of point source measurement protocol; conduct of sampling and analysis; issuance of confirmatory and summary reports; soil sampling and analysis for corroboration to emission data; sourcing and installing temporary CEMS for continuous monitoring of stack emissions.

UNWFP funded project – China, Afghanistan, Pakistan, Bangladesh, Thailand, Iran

Reference Project:  Provision of good and services to mitigate the effects of air pollution in various UNWFP offices

Brief Description:  ESS is responsible for assessing (including sampling and analysis) the indoor air quality in UNHCR offices, consulting and providing mitigation services for client locations.  This project was a contract addition to the UNHCR project based on our positive performance and response to the UNHCR team.